Legal Alert: High-Demand Area: Government rejects REN’s Specific Investment Plan and refers capacity allocation to auction

Articles27 October 2026
Order No. 234/MAEN/2026, issued by the Minister for the Environment and Energy

The Minister for the Environment and Energy has not authorised the Specific Investment Plan (PIE) submitted by REN to strengthen the National Transmission Grid (RNT), for which the total investment was estimated at 419 million euros.

The demand admitted under the exceptional procedure relating to the High-Demand Zone (ZGP) amounts to 4,610.25 MVA, of which 4,583 MVA corresponds to data centres.

Consequently, grid connection capacity is to be allocated through a competitive procedure, by means of the auction provided for in Article 10 of Decree-Law No. 80/2023.

The order also sets out the expected parameters for the auction, specifying the provision of 1,500 MVA, a base bid price indexed to the average grid cost per MVA, and a timeframe extending to the end of 2030.

However, the possibility of submitting an alternative investment plan that addresses the identified risks is not ruled out.


1. Subject matter of the Order:

Order No. 234/MAEN/2026, of 15 October, considers the application for approval of the PIE for the Mainland Portugal ZGP, submitted by REN in May 2026, in accordance with the provisions of Article 126(7) of Decree-Law No. 15/2022 of 14 January, with a view to reinforcing the RNT and meeting the connection requests submitted under the extraordinary procedure for the allocation of connection capacity to the electricity grid.

The decision results in the non-authorisation of the specific investments to reinforce the RNT proposed by REN, thereby ruling out the solution initially envisaged to meet the identified demand and introducing substantial changes to the conditions of access to the grid, with significant consequences in terms of costs, timelines and the economic viability of the projects submitted.


 2. Background

Decree-Law No. 80/2023 of 6 September establishes an exceptional, open, transparent, equitable and competitive procedure for the allocation of connection capacity to the Public Service Electricity Grid (RESP) for consumption facilities located in ZGP areas. In turn, through Order No. 1135/2026 of 26 January, the entire mainland territory covered by the RESP was recognised as a single ZGP.

As part of the convergence phase, provided for in Article 9-A of Decree-Law No. 80/2023, REN concluded that the expressed demand could be met by carrying out additional grid reinforcements and adapting the timetables requested by the interested parties. To this end, it submitted an Investment Plan (PIE) with an estimated total investment of 419 million euros (at full cost), of which 386 million euros relate to specific reinforcements of the National Transmission Network (RNT).

The expressions of interest accepted total 4,610.25 MVA, of which 4,583 MVA relate to data centres and the remaining 27.25 MVA to a priority project, in accordance with the provisions of Article 16(2) of Decree-Law No 80/2023.


3. The decision not to approve the PIE:

The decision not to approve the PIE is not based on the technical merits of the proposed capacity increases, but rather on the allocation of the risk associated with their implementation. Indeed, given that the identified demand relates almost entirely to data centre projects, the risk that these might not materialise was taken into account; in such a scenario, the aim was to safeguard the general public and the National Electricity System (SEN) from the costs associated with the investments made.

As the PIE has not been authorised, the alignment of timetables is no longer feasible; therefore, pursuant to Article 9-A(3) of Decree-Law No 80/2023, capacity allocation must take place through the auction provided for in Article 10 of the same decree-law, without prejudice to the regime applicable to priority projects, namely the 27.25 MVA project, in accordance with Article 16.

Although the preparation of the procedural documents for the auction is the responsibility of REN, with their approval falling to the Energy Services Regulatory Authority (ERSE), the order already indicates that, by the end of 2030, approximately 1,500 MVA of capacity will be made available for auction – a figure deliberately set below the demand identified during the public consultation.


4. Implications:

The rejection of the PIE does not prevent the submission of an alternative investment plan, provided that it duly ensures consumer protection, although, to date, this has not yet happened.

Consequently, as a result of this decision, the allocation of capacity will no longer be based on a grid reinforcement solution tailored to the identified demand, but will instead depend on a competitive mechanism, in which the capacity to be made available will be lower than the expressed needs (1,500 MVA compared to 4,583 MVA). In this context, fierce competition in the tender process is anticipated, as well as the transfer to developers of the financial risk associated with the investment.

This change therefore requires project developers to reassess the economic viability and financial viability of their investments, to adapt their initially planned timetables and to prepare their tender strategies, whilst bearing in mind the contractual commitments whose fulfilment is conditional upon obtaining grid connection capacity.


5. Next Steps:

  • Publication of the auction procedural documents by REN and their approval by ERSE.
  • Preparation by interested parties of their participation in the auction and assessment of any possible courses of action in response to the order.
  • Possible submission by REN of an alternative PIE.